WP1: Consortium Management
Objective
|
The overall objective of this Work Package is the management of the TIARA consortium during the Preparatory Phase project to ensure the achievement of the TIARA-PP objectives with the realization of the defined deliverables in a timely fashion.
To this end, the detailed objectives include
|
WP1 Deliverables
| Nb | Name | Description | Type | Lead beneficiary | Planned month | Achieved month |
| D1.1 | OWSF | Overall Web Site frame ready | Other | CEA | 1 | 1 |
| D1.2 | CAP | Consortium Agreement between Participants ready | Other | CEA | 1 | 1 |
| D1.3 | CCE | Contract of the Consortium with the EC signed | Other | CEA | 1 | 1 |
| D1.4 | OKM | Organization of the Kickoff Meeting | Other | CEA | 1 | 1 |
| D1.5 | IWSF | Internal Web Site Frame ready | Other | CEA | 2 | 3 |
| D1.6 | TTR | Midterm Report | Report | CEA | 18 | 19 |
| D1.7 | FTR | Final Report | Report | CEA | 36 |
WP1 Milestones
| Nb | Name | Description | Type | Lead beneficiary | Planned month | Achieved month |
| MS1 | MTR | Monitoring Tool and documentation Repository | Other | CEA | 4 | 3 |
| MS2 | MGM | Midterm General Meeting | Other | CEA | 17 | 18 |
|
MS3 |
FGM | Final General Meeting | Other | CEA | 34 |